Algonquin Highlands council has approved a project that will see the rehabilitation of Fletcher Lake Landing at a cost of $382,000.
At a meeting on July 16, council was presented with a report that include three options. After a brief discussion council unanimously approved the staff recommended option, the cheapest of the three, which will see the replacement of the existing failed retaining wall with a smaller retaining wall and an 8-foot wide, by 16 foot long dock.
Parks, Recreation and Trails Manager Chris Card says this solution adds extra mooring space, and will provide better navigability at the entrance of the boat launch – two things mentioned in the public survey.
“This achieves exactly what we were looking to achieve based on the survey results,” said Card. “It meets the needs of what we found out from the questionnaire.”
According to Card, the renovations will move the dock from the shallows out into deeper water.
A total of $381,000 was allocated for the project in the township’s 2026 budget.